Nordmann Engineering AT4 Guida rapida alla configurazione

INTEGRATION INSTRUCTIONS FOR NORDMANN AT4
NORDMANN
ENGINEERING
NORDMANN
ENGINEERING
Dampfluftbefeuchter econoVap
Building Management Integration
2559067 EN 1304
@Link


3
Contents
1 Notes for the planning engineer 4
1.1 Overview 4
1.2 Network diagrams 4
1.2.1 BACnet/IP network 5
1.2.2 LonWorks network 5
2 Wiring 6
2.1 Wiring diagram for BACnet/IP 6
2.2 Wiring diagram for LonWorks 7
3 Conguration 8
3.1 ConguringtheNordmannAT4contolunit 8
3.2 Gatewayconguration 9
3.2.1 SettingtheIPaddressandsubnetmask 9
3.2.2 ModifyingtheBACnetNodeID 11
4 Communicationtables 13
4.1 Modbusdataregistertable 13
4.2 Conversiontablesgatewayvariables 15
Ordering form 23

4
1 Notes for the planning engineer
1.1 Overview
The @Link option allows the integration of Nordmann AT4 humidiers into
a BACnet/IP or a LonWorks network. The @Link option features a serial-
interface Gateway which converts the information from the host Modbus
protocol to a specied secondary protocol.
The following protocol options are available and must be specied when
ordering (ordering form see page 23):
Part Number Protocols Part Description
2559069 BACnet/IP BMS AT4 Master set for BACnet /IP
2559070 LonWorks BMS AT4 Master set for LonWorks
2559071 BMS AT4 Slave set for successive units
The following read out and settings functions are available:
Functions AT4
Read out of unit status (operating mode, etc.) X
Read out of service messages X
Read out of analog (%) and sensor (%rh) demand X
Read out of unit type X
Read out actual system request X
Demand signal (%) / sensor signal (%rh) X
Setting the power limitation X
Setting the humidity setpoint (%rh / internal controller) X
Setting the proportional range X
Setting the integral time X
1.2 Network diagrams
It is possible to link up a maximum of 8 units via a single ProtoCessor
Gateway to a building management system. The ProtoCessor Gateway is
connected to the lead unit. All other units (up to a maximum of 8) are daisy-
chained via the NetworkLink terminals.
Since each unit can be separately addressed, it is possible to monitor and
control each unit individually. Different network congurations may be achieved
and are mostly dependant on the type of network present at the site.

5
1.2.1 BACnet/IP network
The diagram below shows the connection of a series of Nordmann AT4
units to an Ethernet network. This is only possible for BACnet and is es-
sentially referred to as a BACnet/IP conguration. Please see chapter 2.1
for additional details.
AT4 / 4...8
AT4 / 4...8
Ethernet (BACnet/IP)
Gateway
(connected to leading unit)
LonWorks
Router LonWorks
Device
LonWorks
Device
LonWorks
Device
Network via shielded twisted-pair cable
Gateway
(connected to leading unit)
AT4 / 1
AT4 / 1
AT4 / 2
AT4 / 2
AT4 / 3
AT4 / 3
1.2.2 LonWorks network
This diagram below shows the connection of a series of Nordmann
AT4 units to a LonWorks network via a shielded, twisted-pair
cable. Please see chapter 2.2 for additional details.

6
2 Wiring
The internal wiring and the installation of the Gateway option in the lead-
ing unit as well as the internal wiring of the successive units are made at
the factory. On site only the gateway must be connected to the network
(BACnet/IP or LonWorks) and the successive units must be daisy-chained
via the NetworkLink terminals using two-wire cables (see corresponding
wiring diagrams).
2.1 Wiring diagram for BACnet/IP
+
–
Net +
Net –
L1 N PE
RJ45 RJ45
D0
D1
D0
D1 D0
D1
RJ45
**
****
to network
external
internal
AT4 / Unit 1
(leading unit) RJ45 Bus cable / Ethernet
24 V DC/AC
power supply
NetworkLink
AT4 / Unit 2 AT4 / Unit 3
NetworkLink NetworkLink
The successive units must be connected to the net-
work by daisy-chain via the NetworkLink terminals! max. 50 m
Blue (Pin 5)
Blue (Pin 5)
Blue (Pin 5)
White (Pin 4)
White (Pin 4)
White (Pin 4)
** Termination of the bus system: to ensure the correct function the bus system must be terminated on both ends. For that purpose a jumper must be set on
the connector “JP1-RS 485 Termination” on the control board of the rst and the last Nordmann AT4 unit in the bus system. On all intermediate Nordmann
AT4 units the corresponding jumper must be removed (see above diagram).

7
Net +
Net –
–
+
RJ45 RJ45 RJ45
D0
D1
D0
D1 D0
D1
+
–
L1 N PE
**
****
to network (via shielded twisted-pair cable)
external
internal
AT4 / Unit 1
(leading unit)
24 V DC/AC
power supply
NetworkLink
AT4 / Unit 2 AT4 / Unit 3
NetworkLink NetworkLink
The successive units must be connected to the net-
work by daisy-chain via the NetworkLink terminals! max. 50 m
Blue (Pin 5)
Blue (Pin 5)
Blue (Pin 5)
White (Pin 4)
White (Pin 4)
White (Pin 4)
2.2 Wiring diagram for LonWorks
** Termination of the bus system: to ensure the correct function the bus system must be terminated on both ends. For that purpose a jumper must be set on
the connector “JP1-RS 485 Termination” on the control board of the rst and the last Nordmann AT4 unit in the bus system. On all intermediate Nordmann
AT4 units the corresponding jumper must be removed (see above diagram).

8
3 Conguration
3.1 ConguringtheNordmannAT4contolunit
The settings described below must be congured on each Nordmann AT4 unit (see Nordmann AT4
operating instructions regarding the operation of the control software):
1. Modbus settings
Select the Modbus menu, Path:
Mainmenu>User>Passwordentry:3562>Modbus>Networking
Set Modbus parameters as follows:
Modbus Adr.: desired Modbus address (range: 1...247)
Important: make sure the Modbus address for each unit is unique!
Parity: None1 (no parity, 1 Stop bit)
The following Modbus parameters of the Nordmann AT4 can not be adjusted and are set to the follow-
ing values:
– 9600 baud
– 1 start bit
– 8 data bits
2. Select the signal source
Select the control settings menu, Path:
Mainmenu>User>Passwordentry:3562>Settings>Controls
Select the parameter “SignalSource” and set it to Modbus.
Networking
Parity :None1
Modus Adr. :1
Esc Set
Controls
Timeout :5s
Hum.Control :External
Lim. Control:On
SignalSource:Modbus
Esc Set
User Code
3562
Enter Number
Conrm with Set
Esc Set
Main Menu
Engineering :Set
Diagnostic :Set
User :Set
Esc Set
User
Settings :Set
Modbus :Set
Maintenance :Set
Esc Set
Modbus
Remote :Set
Networking :Set
Esc Set
Menu
AT4 130kg/h 400V3
Standby
2011-02-15 12.00.00
User Code
3562
Enter Number
Conrm with Set
Esc Set
Main Menu
Engineering :Set
Diagnostic :Set
User :Set
Esc Set
User
Settings :Set
Modbus :Set
Maintenance :Set
Esc Set
Settings
Controls :Set
Cylinder :6564
SC-System :Set
Language :English
Power Limit :Set
Esc Set
Menu
AT4 130kg/h 400V3
Standby
2011-02-15 12.00.00

9
3.2 Gatewayconguration
The protocol conguration is made at the factory, prior to nal testing.
The baud rates are adjusted to the following values:
Protocol Baud rate
BACnet/IP 10 / 100 BaseT
LonWorks 78125 bps
3.2.1 SettingtheIPaddressandsubnetmask
For BACnet/IP and LonWorks application, an IP address and the subnet
mask must be assigned to the gateway in order to access it. The IP ad-
dress and subnet mask may be assigned at the factory or can be modied
at any time via the integrated FieldServer GUI (Graphic User Interface) of
the ProtoCessor.
To congure the IP address and the subnet mask via the integrated Field-
Server GUI of the ProtoCessor proceed as follows:
1. Connect the ProtoCessor gateway to a PC using an Ethernet cross-
over cable or directly to the network using a straight cable.
2. The default IPaddress of the ProtoCessor Gateway is set to 10.232.72.172,
Subnet Mask is 255.255.0.0.
Make sure your PCis in the same IP network as the ProtoCessor Gate-
way; otherwise assign a static IP address to your PCon the 10.232.72.0
network.
3. Power up the ProtoCessor Gateway.
4. Open your internet browser and enter the IP address of the gateway
(by default ex factory 10.232.72.172), then conrm the entry with the
Enter key.

10
5. The FieldServer GUI will be started.
6. Select the menu point “Setup > Network Settings” in the “Navigation
Tree”. Enter the appropriate IP-Address and subnetmask. To activate
the new settings, click rst on the button <Update IP settings> and then
on the button <System Restart>. After restart the gateway is congured
to the new IP address and subnetmask.
7. In order to access the ProtoCessor gateway, the IP address of your
laptop must be set to the same network as the ProtoCessor.
Altri manuali per AT4
2
Indice
Altri manuali Nordmann Engineering Umidificatore

Nordmann Engineering
Nordmann Engineering ES4 Come usare

Nordmann Engineering
Nordmann Engineering AT4 Manuale utente

Nordmann Engineering
Nordmann Engineering AT4 Manuale utente

Nordmann Engineering
Nordmann Engineering Omega Pro Series Manuale utente

Nordmann Engineering
Nordmann Engineering Omega Pro Manuale utente

Nordmann Engineering
Nordmann Engineering Omega Pro Manuale utente

Nordmann Engineering
Nordmann Engineering MinAir Manuale utente