We Care Solar Suitcase Manuale utente

We Care Solar | Jan 2019
We Care Solar Suitcase®Installation Guide
www.wecaresolar.org
WCS-SC3

We Care Solar® promotes safe motherhood
and reduces maternal mortality in energy
poor regions by providing healthcare workers
with reliable lighting, mobile communication,
and medical devices using solar electricity.
The We Care Solar Suitcase® provides
highly efficient solar energy systems to
health facilities in areas without reliable
electricity. Our durable, easy-to-use
Solar Suitcases power medical lighting,
mobile communication, and essential
medical devices.

We Care Solar | Jan 2019
Installation Planning
Before Installation Day
• Ensure the in-charge and
midwives will be present
on installation day
• Check if the facility still
needs a Solar Suitcase; it
is possible the facility may
have recently received
alternate solar power or
been connected to the grid
• When possible, bring an
extra solar panel and Solar
Suitcase for backup and
teaching
• Bring food and water in
case there is little available
at the site
Identify installation team
2-3 technicians + 1 driver
Location planning
Call the clinic at least
one day in advance
Prepare and load tools
Review preparation checklist
Solar Suitcase + 1 extra for teaching healthcare facility staff and as a backup
1
2
3
4
5
Solar Panel(s) + 1 extra in case of breakage
Toolkit including drills and ladder
Make sure the drill batteries are charged and you bring the charger
Installation tracking sheet and other documents like baseline survey if applicable
Camera for taking photos at installation
04
Preparation Checklist

We Care Solar | Jan 2019
Installation Planning
After Installation
Installation Day
Leave early
Avoid working in the hot
afternoon sun. Leave time
for unexpected delays.
Teach healthcare workers
Train healthcare staff on
how to use and maintain
the Solar Suitcase
Complete paperwork
Please take the time to
complete the necessary
paperwork
Review nal
installation checklist
Checklists reduce
errors – use them!
Take photos
Take photos of installation.
Show us your good work!
Depart prior to dark
Re-organize tools
and load vehicle
Arrive and introduce
yourselves to the person
in charge of the clinic
Take a tour of the clinic
with the medical team
Plan the installation
Ask healthcare workers to
show you where they do
procedures to determine
the best place to install the
lights and Solar Suitcase
Organize team
Assign responsibilities
to roof lead, ground lead,
and teaching lead
Clean up the site
Take away debris
and re-organize any
furniture moved
Complete installation
Review installation
checklist for solar panel,
Solar Suitcase, lights,
and last steps
05

We Care Solar | Jan 2019
Installation Overview
06
The Lights must be placed where
they are most needed at the facility.
Talk with the midwife to determine
the best location for each light. Light
cables are 33 feet (10m) in length.
Primary locations:
• Delivery bed
• Resuscitation table
• Pre or post delivery room
Secondary locations:
• Entrance
• Waiting area
• Hallway
• Oce
The Solar Suitcase should be
mounted in a secure and dry area of
the facility and at a height where all
healthcare workers can easily turn
on lights and charge appliances
Light Expansion Box should be
mounted in a convenient location
such as the building entrance, hallway,
or delivery room. The Light Expansion
Box cable is 40 feet (12.2m) in length.
The Homerun Cable is 40 feet
(12.2 meters) and must reach from
the solar panel to the Solar Suitcase
The Solar Panel must be installed
where it will get sun all day long
A
A D
E
D
E
B
C
B
C

We Care Solar | Jan 2019
Solar Panel Installation
Parts & Tools Required
From the Solar Suitcase
From the Large Tool Bag
07
Homerun Cable
(4) L Brackets
Cordless Drill Driver Inclinometer
Zip Ties
1/4" Nuts
and Bolts
#12 x 3" Roof Screws
Silicone
1/4“ Standard Drill Bit
1/8” Standard Drill Bit
1/4" & 5/16” Nut Drivers
Safety Glasses Step Drill Bit
Wire Stripper
Slip Joint Plier WrenchHammer
Electrical
Tape
Cable Guard
Marker
#8 x 1-1/4"
Self-Tapping Screws
Actual size
Actual size
Actual size
Actual size
Actual size

We Care Solar | Jan 2019
Solar Panel Installation
Safety First
If roof is too steep or too weak for you to work on safely you can:
Mount the solar panel on the eave of the roof while
standing on the ladder. We do NOT want you to risk
getting hurt.
Mount the solar panel on a post or build a structure
near the clinic to mount the solar panel and then
route the homerun cable into the clinic
Look
Identify any potential dangers.
This includes power lines,
skylights, wasps, bats, holes in the
roof, or rusty spots on the roof.
Be Aware
Ladder Safety
Do not touch electricity lines
with your body or ladder
Do not walk near or over
skylights
Avoid wasp nests, attics with
bats or rodents. They may harm
you during installation and can
also eat through cables.
Plan
Work safely — make a plan
with your team on how to
work safely and communicate
with your team
08
• When you use a ladder, be careful and make sure it is
stable before you climb
• Only one person should be on the ladder at a time
• When standing at the base of the ladder, your outstretched
arms should be able to reach the ladder
• Climb with your eyes facing the ladder
• Have someone hold the ladder
• When getting off the ladder onto the roof, step around the
ladder and not over the top of the ladder

We Care Solar | Jan 2019
Solar Panel Installation
Using the Drill
Make sure to point
the drill straight
Unlock
Lock
09
Speed
Use speed #1 (slow) for attaching
screws and for drilling into concrete
Use speed #2 (fast) and light
pressure for drilling the solar panel
frames, walls and ceilings
Quick Mode
Adjustment
Torque Adjustment Ring
Use lower number settings for
attaching screws. Increase as
needed to drive the screw to
the correct depth.
Use higher number settings for
drilling holes on the frame of
the solar panel or drilling into
the wall or ceiling
Trigger
Rechargeable
Battery
Direction Mode
Forward/Lock /Reverse
Chuck
Adjustment
Wear safety glasses when you are drilling
!
:
:
:
Hammer mode for masonry
and concrete
Screw drive mode for
attaching screws
Drill mode for
drilling holes

We Care Solar | Jan 2019
Solar Panel Installation
Where to Place the Solar Panel
10
The solar panel must be placed where it
will receive the most direct sun all day long
The L feet can be attached to the top and bottom of the solar panel or the sides of
the solar panel. The solar panel must be mounted to the wood frame to the roof below.
The solar panel must be mounted on a
slope of 10 to 15 degrees from horizon
to allow for rain to run off
10-15˚
Use inclinometer to
measure the slope
Do not place the solar panel where it
will be shaded by a tree or another building
Install the junction box close to the
ridge/high part of the roof
High
Junction Box
Low