INSTALLATION PROCEDURES FOR
THE
POLARIA
AWNING
Warning:
PLEASE ENSURE SNOW OR ICE REMOVAL OF STRUCTURE IN
CASE OF EXCESS SNOW OR ICE FOLLOWING A STORM !
FAILURE TO FOLLOW THESE PROCEDURES COULD RESULT IN
INJURY !

MULTIPLE AWNINGS
-
1701, de l’industrie
-
Beloeil ( uébec)
-
J3G 4S5
Phone : 450-446-4182 or 1-866-446-4182 - www.multipleawnings.com
Rev. 1 as of 2009-03-02 Page 2 of 35
INSTALLATION PROCEDURES FOR
THE POLARIO AWNINGS
PAGE
TOOLS RE UIRED …………………………………………………………………..………………… 3
LIST OF COMPONENTS …………………………………………………………………………… 4
Brackets and hardware ………………………………………………………………….. 4
Roof components ………………………………………………….…………………………… 6
INSTALLING THE WALLS………………………………………………………………………… 8
THE DOOR OPENING ………………………………………………………………………………… 11
INSTALLING CAPPING……………………………………………………………………………… 12
Install the interior capping……………………………………………………………… 12
Install 90˚ exterior capping in each corner………………………………… 13
Install double exterior capping on each side………………………………… 14
INSTALLING THE HEAD (if your installation is a wall mount)…………… 15
INSTALLING THE HEAD (if your installation is under cornice)………… 18
INSTALLING THE BEAM……………………………………………………………………………… 21
INSTALLING THE VINYL ROOF………………………………………………………………… 24
TIGHTENING THE VINYL ROOF ……………………………………………………………… 24
INSTALLING THE DOOR (depend what kind you have)………………………… 25
Install the hinging door……………………………………………………………………… 25
Install the sliding door……………………………………………………………………… 27
ADVISES…………………………………………………………………………………………………………… 35

MULTIPLE AWNINGS
-
1701, de l’industrie
-
Beloeil ( uébec)
-
J3G 4S5
Phone : 450-446-4182 or 1-866-446-4182 - www.multipleawnings.com
Rev. 1 as of 2009-03-02 Page 3 of 35
RE UIRED TOOLS
1power drill
1drill bit 5/32’’ *
1 drill bit 3/16’’ for cement *
15/16’’ drill bit adaptor*
15/16’’ hex wrench ( or stamped aluminium key ) *
1drill bit 1/2”
1drill bit number 2 *
1 sharp knife
1pair of safety glasses
1measuring tape
1 chalk line
one 8 foot long ladder
one small 3 foot ladder
•tools that are included with shipment

MULTIPLE AWNINGS
-
1701, de l’industrie
-
Beloeil ( uébec)
-
J3G 4S5
Phone : 450-446-4182 or 1-866-446-4182 - www.multipleawnings.com
Rev. 1 as of 2009-03-02 Page 4 of 35
LIST OF COMPONENTS
Brackets and hardware:
5/16’’ Self taping screws, ¾’’ long 130
Cement screws 1 ¼’’ long 60
#8 Metal screws square head, 3” long 20
(
U) Brackets for fixing 15
#8 Metal screws, square head, 1 ¼’’ long 60
90˚ Bracket inserts 2

MULTIPLE AWNINGS
-
1701, de l’industrie
-
Beloeil ( uébec)
-
J3G 4S5
Phone : 450-446-4182 or 1-866-446-4182 - www.multipleawnings.com
Rev. 1 as of 2009-03-02 Page 5 of 35
(L) Supports with four holes 10
Gauge used to fix the panels 1
Gauge used to fix the beam 1
Upper door parts of 35’’ long with cappings 1
Handle (only for a hinging door) 1
Self-taping screws of 3/8’’ long (for hinging door) 8

MULTIPLE AWNINGS
-
1701, de l’industrie
-
Beloeil ( uébec)
-
J3G 4S5
Phone : 450-446-4182 or 1-866-446-4182 - www.multipleawnings.com
Rev. 1 as of 2009-03-02 Page 6 of 35
R
oof components
Head part of the structure 1
Rafters ultra 2.5” x 1.5” 8
Cappings for rafters ultra 16
Corner cappings 2
2
1
1 – Cornice 1
2 -
Flash attachment systems
1

MULTIPLE AWNINGS
-
1701, de l’industrie
-
Beloeil ( uébec)
-
J3G 4S5
Phone : 450-446-4182 or 1-866-446-4182 - www.multipleawnings.com
Rev. 1 as of 2009-03-02 Page 7 of 35
WARNING
Please make sure that your balcony is level. This is a pre-requisite for this
modular type installation
WARNING
Depending which king of floor you have, it will be required to install
aluminium flashing on the floor to avoid any water infiltrations. For
acement floor, it is not required, you will only have to apply caulking inside
your awning. To install the aluminium flashing, be sure to keep at least
2 ½ “ (depth of panels) inside your balcony. Make sure that the flashing
follows as well your balcony. This is necessary to expel water. When all
your panels will be installed, you will apply caulking all around your awning.
With the help of the aluminium flashing, the water will get out easily and
avoid
water infiltration.

MULTIPLE AWNINGS
-
1701, de l’industrie
-
Beloeil ( uébec)
-
J3G 4S5
Phone : 450-446-4182 or 1-866-446-4182 - www.multipleawnings.com
Rev. 1 as of 2009-03-02 Page 8 of 35
INSTALLING THE WALLS
•Before fixing the first
panel, includes are two
additional legs of 78’’ high.
Each of them must be
fixe un er the gables an
to the wall
. The straight
face must be edge to edge
with the panel. The other
face must be on the wall. So
you will start by fixing one leg, and then install
the first panel beside.
PANELS
HOUSE
BALCONY
Aluminium flashing
Fixe to the wall
with screws of 3 ‘’
long

MULTIPLE AWNINGS
-
1701, de l’industrie
-
Beloeil ( uébec)
-
J3G 4S5
Phone : 450-446-4182 or 1-866-446-4182 - www.multipleawnings.com
Rev. 1 as of 2009-03-02 Page 9 of 35
•Start by fixing the first panel on the floor. Make sure that it is well
positioned. The panels are fixed to the floor with U brackets. First, the U
brackets are fixed to the floor, and
then the panel is fixed to the U
brackets (like as shown on the
following pictures).
•
•
•You will have to
fix the panel and
the leg together
with 3’’ square
headed metal
screws.
•
•As a reference, the screen is always facing outwards and the polymer
windows facing inwards.
•Once your first panel is inserted in your brackets and
fixed with 5/16” self taping screws, you are ready to
install the second panel. Make sure that both panels are
aligned edge to edge, this is necessary to install the
double capping later properly.
Different floor types:
•CEMENT FLOOR: you will need to pre-drill a hole with an impact drill
and use special cement screws.
•FIBREGLASS ON WOOD: make sure you use the length of screw that
is appropriate to your floor structure. Apply caulking before to fix the
screws.
Use the chalk line
as a reference to be
sure that your wall
will be straight
The U bracket
must be fixed
inside the interior
line to insert the

MULTIPLE AWNINGS
-
1701, de l’industrie
-
Beloeil ( uébec)
-
J3G 4S5
Phone : 450-446-4182 or 1-866-446-4182 - www.multipleawnings.com
Rev. 1 as of 2009-03-02 Page 10 of 35
•Install the second panel, fix both panel
together with three
#8 square head
metal screws of 3’’ long. Pre-drill one of
them with a drill bit 5/32” inside the
window lock to conceal the screws. Repeat
this step 3 times.
•Now your first wall is completed and it’s time to start the second wall.
Before fixing the U bracket, be sure that the panel is positioned at 90° to
the first wall as shown. This is necessary for installing the corner capping
later on.
Top view
•Fix the simple interior capping before installing both panels together.
•Fix three “L trims” with four holes on the side of the panel, those will be use
to fix the two walls together. Fix another L support onto the floor to secure.
Fixed right in the corner Fixed with 5/16” self taping screws
I
t should have a little chink, easier to snap the 90°capping
Exterior capping
to be installed
later panel
Panel
Well positioned with a perfect
90°
Use a pair of grip to hold
the panels together