Penner Cascade Alcove Guida

PENNER PATIENT CARE, INC
Box 523 / 102 Grant St.
Aurora, NE 68818
360745A Revision A – 10/26/07
1-866-PENNERS 1-866-736-6377 1-800-732-0717
Web Site: www.pennercareinc.com
ALCOVE with AQUA-AIRE
Installation / Assembly
Instructions
361910-1A, 361910-1I, 361910-XA, 361910-XI

2
2
Table of Contents
TABLE OF CONTENTS..............................................................................................................2
INTRODUCTION:........................................................................................................................3
TERMINOLOGY AND SYMBOLS MEANINGS ....................................................................3
TUB CONTROLS:........................................................................................................................3
BASIC DIMENSIONS:.................................................................................................................3
ROUGH IN SPECIFICATIONS:................................................................................................5
DRAIN REQUIREMENTS .…………………………………………………………………….9
HOT AND COLD WATER SUPPLY REQUIREMENTS:....................................................10
ELECTRICAL REQUIREMENTS...........................................................................................10
UNPACKING THE TUB............................................................................................................12
WATER SUPPLY HOSE CONNECTIONS ............................................................................11
ANCHORING THE TUB – “ALCOVE INSTALLATION” (2 OR 3 WALLS)...................11
ANCHORING THE TUB – “PENINSULA INSTALLATION” (1 WALL – BACK)..........13
ANCHORING THE TUB – “PENINSULA INSTALLATION” (1 WALL – SIDE)............14
ELECTRICAL CONNECTIONS..............................................................................................14
WATER SUPPLY AND DRAIN CONNECTIONS: ...............................................................14
FINISHING UP:..........................................................................................................................15

3
3
Introduction:
These instructions are for the installation of a Cascade Alcove tub in various configurations as
shown below in figure 1. Follow the instructions for your particular installation configuration.
Figure 1
Terminology and Symbols Meanings
When the terms “left” or “right” are used with reference to the tub, this means left or right as
you look when seated in the tub.
Meaning: Safety warning. Failure to understand and obey this warning may result
in injury to you or to others.
Meaning: Failure to follow these instructions may cause damage to parts
or systems.
Note: Refer to the “Tub Controls” section of this manual for the location of any of the controls
referenced.
Tub Controls:
Basic Dimensions:
CAUTION
TUB FILL ON/OFF BUTTON
FILL
SPOUT
A
Q
UA-AIRE ON/OFF
FILL /SHOWER
TEMPERATURE
READ-OUT
SHOWER ON/OFF
HAND SHOWER
OVER FLOW
DRAIN PLUG CABLE
RINSE BUTTON
DISINFECT BUTTON
Figure 2
Tub Controls
MIXING VALVE
TEMPERATURE CONTROL

4
4
Figure 3
Basic Dimensions Cascade Alcove

5
5
Plumbing Requirements:
It is required that a licensed plumber make all plumbing connections. He can select the
best method of connection and if Reduced Pressure Zone Backflow Preventers are required.
Rough in Specifications:
(Alcove Installation 2 or 3 walls and Peninsula Installation 1 wall – end)
Figure 4
Rough-in Specifications
Cascade Alcove and Peninsula Installation – 1 wall –
back
(Reference figure 1)

6
6
Figure 5
Rough-in Specifications Peninsula Installation – 1 wall – Side plumbing from the floor
(Reference figure 1)
Figure 6
Rough-in Specifications Peninsula Installation – 1 wall – Side plumbing from the back wall

7
7
Figure 7
Drain requirements
The tub is equipped with a 2” nominal (2 3/8” O.D.) PVC drain pipe. Figure 3, 4 & 5 show
three different options for roughing in the drain pipe – from the floor, from the side wall, and
from the back wall. The connections for those two options are shown in figures 7 & 8
It is required that a licensed plumber make all plumbing connections. He can select the
best method of connection for the particular situation.

8
8
Figure 8
Drain pipe from the wall.

9
9
Figure 9
Drain pipe from floor at 20” location.
Hot and cold water supply requirements:
3/4” supply lines with on/off valves with 3/4” NPT female threads. We recommend 3/4” ball
valve with 3/4” NPT female ports. (Valves supplied by others.) See figure 4, 5 & 6 for
recommended locations.
For optimum performance, dynamic pressures should be nominally equal between hot and cold
supplies.
Maximum static supply pressure: 145 PSI.
Maximum dynamic/maintained supply pressure: 81 PSI.
Maximum supply Hot water temperature: Consult local requirements for maximum allowed
supply temperatures. (Not recommended over 120oF)
Electrical requirements
The Cascade Alcove tub is rated 6.5 amps at 120 Volts AC.
A 15 amp GFCI circuit is required.
See Figure 4, 5 & 6 for the location of a small junction box from which the power supply will
come. It will be connected via flex conduit to the field wiring box of the tub. It is located
inside the side access door of the tub below the larger electrical box. See figure 9.

10
10
It is recommended that the power wires and conduit be connected to the supply box prior to
moving the tub into place. Then, connect the conduit to the tub’s field wiring box and make the
final wiring connections after the tub is in place.
A licensed electrician is required to make all electrical connections.
Figure 10
Electrical Supply
Alcove Installation 2 or 3 walls
Or Peninsula installation – one wall – end
(Reference Figure 1)