Emona Instruments Pty Ltd ProTag PAC-3P Manuale utente

1
ProTagTM
PAC-3P 3 Phase Appliance & Extension Lead Tester
User Manual
Made in Australia by:
Emona Instruments Pty Ltd
www.emona.com.au www.protag.com.au

2
Contents
1.0 Introduction 3
2.0 PAC-3P Specifications 3
3.0 User Note 3
4.0 Safety 4
5.0 Accessories 5
6.0 Unit Description 6
7.0 Using the PAC-3P Leakage Tester 8
7.3.1 Testing 3 Phase APPLIANCES 8
7.3.2 Testing 3 Phase EXTENSION LEADS 11
8.0 Recording Results on the Seaward PrimeTest 300 14
9.0 Service & Calibration 16

3
1.0 Introduction
The PAC-3P is a portable, battery powered 3 phase stand-alone test instrument for
performing earth continuity and earth leakage current tests as required by AS/NZS 3760,
including:
Earth continuity @ 200mA
Leakage Current Test – Mains-powered
The unit conducts a sequence test, starting with an earth continuity test and then proceeding
with the leakage test. It indicates Pass/Fail and the actual measured readings on the LCD
display and provides on-screen user prompts. It includes safety features such as preventing
a leakage current test in event of a failed earth continuity test result. 20A and 32A extension
lead test adaptor is included with an earth test pin terminal, which eliminates the need for
probing of the extension lead earth.
2.0 PAC-3P Specifications
Display LCD
Indication PASS/FAIL and measured values
Operation 2 push buttons
Earth Continuity Test:
Display Range 0.1ohm to 20ohm
Test Current 200mA
Pass/Fail Limit 1ohm
Accuracy better than 5% at 1ohm
Leakage Test:
Display Range 0.15mA to 9.99mA
Pass/Fail Limit 5mA
Accuracy better than 5% at 5mA
Power Source 2x9V batteries
Accessory 20A and 32A extension lead test adaptor with earth test pin
3.0 User Note
This instrument and its operating instructions are intended for use by adequately
trained personnel who are AS3760 competent.
It is important to follow the documentation and operating instructions to avoid danger.

4
4.0 Safety
In order to ensure safe operation of this instrument, all WARNING and CAUTIONS must be
observed at all times.
CAUTIONS
The PAC-3P is intended for use in a dry environment only
The PAC-3P BLACK earth clamp must always be used to provide earth continuity.
Check the PAC-3P and all associated cables and leads and appliance/lead under test
before conducting each test. Do not use if there are signs of damage.
When safe operation of the PAC-3P is no longer possible it should be immediately shut
down and secured to prevent accidental operation.
It must be assumed that safe operation is no longer possible:
•if the instrument or leads show visible signs of damage or
•the instrument does not function or
•after long periods of storage under adverse environmental condition
WARNINGS
If the test equipment is used in a manner not specified in this user manual, the
protection provided by the equipment could be impaired.
Read this user manual carefully, otherwise the use of the instrument may be
dangerous for the operator, the instrument or for the equipment under test.
Consider all generally known precautions in order to avoid risk of electric shock when
dealing with hazardous voltages.
Do not use the instrument in supply systems with voltages higher than 550V.
Do not open unit, no other user serviceable parts.
Hazardous voltages exist inside the instrument. Disconnect all test leads, remove the
power supply cable and switch off the instrument before replacing batteries
Always ensure that the appliance or lead under test is electrically isolated
High voltages are present at the L1, L2 and L3 terminals when connected to the
mains. Always use the adaptor provided to test extension leads, do not use the
“probing” method.
Do not touch any exposed metal parts of the PAC-3P during testing.
Do not leave the PAC-3P permanently connected to the mains. Always disconnect all
test leads immediately after use.

5
5.0 Accessories
5.1 Standard Contents
The PAC-3P tester is supplied with the following items:
1 x PAC-3P unit
1 x PAC-3P-ELA Extension Lead Test Adaptor Set (20A/32A)
1 x User Manual
5.2 Type of Batteries
2 x 9V batteries
Replacement of batteries:
1. Pull the battery compartment up (Figure 1 – No 6)
2. Withdraw battery from its case
3. Put a new 9V battery into the case
4. Insert the battery case back into the compartment
5.3 Cleaning Instructions
You can clean the instrument regularly or as needed.
CAUTION: Please ensure unit is OFFLINE and disconnected from mains power.
When the panel surface or cover becomes soiled, wet piece of soft cloth with a water-diluted
neutral detergent and wipe the surface gently.
Do not put volatile solvents such as thinner or benzene. They may discolour the unit surface
coating and/or erase printed characters.
Do not wipe any exposed metal with excessive liquid.
After cleaning, wait until unit is completely dry prior to use.

6
6.0 Unit Description
6.1 PAC-3P 3 PHASE LEAKAGE TESTER
Figure 1
1. 20A Plug to Mains
2. 32A Plug to Mains
3. Earth Continuity Clamp
4. 20A Test Socket (for Appliances/Leads)
5. 32A Test Socket (for Appliances/Leads)
6. 9V Battery Compartments
7. LCD Screen
8. GO test key
9. Power ON/OFF button
10. SELECT test key
1
2
3
4
5
9
8
10
6
7

7
6.2 PAC-3P-ELA 3 PHASE EXTENSION LEAD TEST ADAPTOR
Figure 2
1. 20A Plug Test Lead
2. 32A Plug Test Lead
3. Earth Test Pin Terminal (Attach Earth Clamp Here)
1
2
3

8
7.0 Using the PAC-3P Leakage Tester
7.1 Power On PAC-3P Tester
To turn the PAC-3P on, switch the power button (Figure 1 – No 9) to the ON position.
NOTE: The LCD screen will light up when unit is on.
NOTE: If battery is indicated as low, please change or replace with new batteries.
7.2 Preliminary Electrical Safety Check
Always ensure that the appliance or lead under test is electrically isolated
7.3 Earth Continuity & Leakage Current Measurements
WARNINGS
For leakage current measurement, the equipment rating to be measured shall NOT exceed:
•For 3-phase 20A plug and socket: 415V/20A
•For 3-phase 32A plug and socket: 415V/32A
7.3.1 Testing 3-Phase APPLIANCES
Procedure:
1) Plug the 3-phase appliance under test into one of the PAC-3P sockets (20A or 32A).

9
2) Clip earth clamp to exposed metal of your 3-phase appliance.
3) Check that PAC-3P is switched ON (Figure 1 – Button 9).
4) Please use the “SELECT” button until “GO: APPLIANCE TEST” is selected on
screen.
5) Press “GO” to confirm.
6) Press “GO” – The PAC-3P will check earth continuity (Rpe < 1Ωis a PASS).
7) Press “SELECT” – If Rpe = PASS it will continue to the next stage of testing.
If Rpe = FAIL the PAC-3P will exit the testing procedure.
NOTE: If the Rpe has failed please check and verify your earth clamp connection.
8) Connect the PAC-3P mains plug (20A or 32A, depending on which test socket you
are using) to an appropriate 3-phase power supply.
NOTE: Do NOT press “SELECT”, unless you want to exit the test.

10
9) When MAINS is connected, the following message will appear on-screen.
10)Press “GO” to proceed with current leakage measurement.
11)After a few seconds, the measurement will be displayed on screen and indicate
whether it is a PASS or FAIL.
12)Turn off the 3 Phase mains supply and then safely disconnect the PAC-3P from the 3
Phase mains socket.
13)Record the reading in your logbook or on your logging tester.
For PrimeTest 300, refer to Section 7.4.
14)Press: “SELECT” to exit to the main menu.
Indice
Manuali Apparecchiature di prova popolari di altre marche

SMART
SMART KANAAD SBT XTREME 3G Series Manuale utente

Agilent Technologies
Agilent Technologies BERT Serial Manuale utente

Agilent Technologies
Agilent Technologies N3280A Manuale utente

Vernier
Vernier Go Direct Voltage Manuale utente

Lifeloc
Lifeloc R.A.D.A.R. Manuale utente

Fluke
Fluke T5-600 Istruzioni per l'uso e l'installazione