ATTENTION!!!: before removing the control, to ensure that the operator is switched off and is not powered
pneumatically or electrically. Also use appropriate lifting systems.
Remove the valve from the pipeline and place it on the workbench with the closure (02) upwards. Fix the
valve so that it does not move.
Remove the nuts (12). Lift the closure (02) with a proper lifting system.
Place the closure on the table and remove the O-ring (14) and seal graphite (13) demaged.
Clean very well and lubricate all the seal graphite and the O-rings. Clear the housing (slot). Now first insert
the new seal graphite (13) and then the O-ring (14) in their housing.
Lift and insert the closure (02) on the stud bolts (10) so that the closure itself is inserted on the body (01) and
that the closure is inserted on the housing.
Verify the correct alignment of the closure respect to the cylindrical pin (24) of the bearing retainer. When they
are aligned, to go down slowly the closure.
Gradually and evenly tighten the nuts (12). We recommended to follow a sequence of cross closing, using a
torque wrench. The tightening torque is defined according to the material of the screw.
In order to replace the second side, overturn the valve and carry out the above operations.
Make an opening-closing movement, the ball should move easily. After the valve installation, make a pressure
test of the same, making sure there are no leakage.
If ok, proceed to the installation of the adapter and the control.
4.2 – THE SEATS+INSERT (06+05)
Bring the valve to the closing position and discharge the pressure from the pipeline both upstream and
downstream.
Discharge the pressure from the body leaving the vent bleeder valve open (35).
Remove the control and the adapter, if equipped.
ATTENTION!!!: before removing the control, to ensure that the operator is switched off and is not powered
pneumatically or electrically. Also use appropriate lifting systems.
Remove the valve from the pipeline and place it on the workbench with the closure (02) upwards. Fix the valve
so that it does not move.
Remove the nuts (12). Lift the closure (02) with a proper lifting system.
REMOVING THE CLOSURE, EVEN REMOVING THE SEAT (the seat is positioned within the enclosure).
Now it is possible to remove the seat (06+05) with the seat springs (21) the O-ring (23) and graphite seat
gasket (22) ATTENTION: the seat springs (21) must remain in their housings. Clean and lubricate the new O-
ring and insert the same in to the slot. Do the same for the graphite seal ring.
Check that all springs are in its housing, if necessary grease them slightly.
Clean and lubricate the surface of the closure where the seat will be insert.
Positioning the seat (06+05) on the closure (02), perfectly in axis.
Manually push the seat into the housing of the closure, if necessary help themselves with a rubber mallet.
The seat must enter straight.
Now lift and insert the closure (02) on the stud bolts (10) so that the closure itself is inserted on the body (01)
and that the closure is inserted on the housing.
Verify the correct alignment of the closure respect to the cylindrical pin (24) of the bearing retainer. When they
are aligned, to go down slowly the closure.
Gradually and evenly tighten the nuts (12). We recommended to follow a sequence of cross closing, using a
torque wrench. The tightening torque is defined according to the material of the screw.
In order to replace the second seat, overturn the valve and carry out the above operations.
Make an opening-closing movement, the ball should move easily. If ok, proceed to the installation of the
adapter and the control. After the valve installation, make a pressure test of the same, making sure there are
no leakage.