Table 1 Installation
Tools Needed
Heavy machinery (backhoe or front-end loader) or shovel, as appropriate
Sledgehammer
4 × 4 wood boards (for stainless steel Divergence Control Tube [DCT])
Flat blade (or other utensil)
Diatomaceous earth (DE)
Tarp
Rope or strap, approximately twice the length of the intended installation depth
Flat head screwdriver
Cap, plug, or crimp for the end of the sampling tube
Preparation
Select Location
Choose the desired location based on relevant details, including representative
position for sensor installation, vegetation cover throughout the season,
minimal interference, etc.
Determine Installation Depth
Decide installation depth (Section2.1.1).
Select Location for DCT Soil
Select a separate location close enough to the installation location that soil
properties are similar, but far enough away that excavation activities do not
impact the installation location (e.g., 10 m apart). Both the amount of sample
and its chemical composition need to be representative of deep drainage at
the installation location.
Option 1: Collect Intact Soil Monolith
NOTE: This option is only for a Stainless Steel DCT.
Excavate to the optimal level for the top of the DCT (Section2.1.1).
Place the DCT on the exposed soil in the excavated hole.
Place one or more wood boards on top of the DCT to distribute the insertion
force to avoid damaging the DCT.
Press or pound the DCT into the soil a few inches using heavy equipment or a
heavy sledgehammer, as appropriate.
Remove the soil around the portion of the DCT that has been inserted.
Alternate pounding and digging until the DCT is fully inserted into the soil.
NOTE: In some situations (e.g., stony soil),it may not be possible to push or pound the DCT
into the soil to collect an intact monolith.In this case,a repacked monolith is the only option.
Dig a hole around the DCT large enough to access the bottom edge.
Use a flat blade or other utensil to cut the soil at the bottom edge of the DCT,
resulting in a flat soil face at the lower boundary of the DCT.
Lift the DCT with intact monolith out of the hole.