6. Installation
6.1. General
The assembly has to be carried out following the corresponding general technical
regulations for pressure measuring devices (e.g. DIN 16255 or EN 837-2).
While screwing in at the connection point, the required force must
not be applied using the housing, instead only use the key areas
designated for this purpose.
The installation location of the Level Meters should be easily accessible.
To avoid display deceleration time the distance between pressure withdrawal and
pressure connection should be kept small.
Between the pressure withdrawal point and the measuring unit, a shut-off device
should be introduced which allows a renewal and null-point check of the running
system. Up to the final commissioning, the shut-off equipment should remain
closed in the measurement piping. If pressure peaks are expected, suitable
protective equipment may be considered, such as a pressure peak suppressor or
a similar device. Alternatively, pressure measuring units with damping-liquid filling
such as a glycerine manometer may be provided.
The piping up to the measuring unit should provide a vibration-free, stable
attachment; otherwise, a wall bracket should be provided
The attachment of the Level Meters is to be executed in such a way that the
admissible operating temperature does not violate min. and max. limits. In
addition, Level Meters and stop valve should be protected through sufficiently
long dimensional piping or water-bag pipes. The temperature conditions can
influence the display accuracy.
An additional liquid column may affect the gauge only if this pressure is noted on
the scale. In the unfavourable case, the result of measurement is falsified.
For sealing of measuring unit's connections, sealing disks or sealing-edge-rings
are utilised. The connection is recommended with stress-sockets or union-nuts;
with that the Level Meter can be placed in the best reading position. During
screw-in or screw-out, the force must not be exerted on the Level Meter housing,
rather applied only over the four hexagonal connection-clips.
Before attaching the gauges, the Level Meter piping should be cleaned with the
Medium to be measured or with clean compressed air. While squeezing off or
blowing through the piping or containers, the gauge may not be over-pressed. If
the expected pressure is higher, the Level Meter must be removed or locked off.